INSTALLATION
01 Jan 14 3-3
DE-7200VFDCentrifuge
INSTALLATION SEQUENCE
Following is the sequence of steps for installing the centrifuge. The sequence presented may vary
depending on the user’s facilities and previous experience with this type of equipment.
1. Read and understand all safety information in Section 2 before installing and operating this
equipment.
2. Read and understand the equipment handling procedures in this section before lifting and
positioning the equipment.
3. Position and level equipment at installation site.
4. Remove shipping components, and lower and secure the rotating assembly bearing pillow
blocks to the base.
5. Adjust drive belt (refer to Section 5).
6. Connect liquid discharge line.
7. If discharge duct is to be used, connect duct to solids discharge chute.
8. Install flexible joint, feed tube, and piping connections for slurry feed, polymer injection, fresh
liquid cleanout, and sampling port.
9. Select and install feed pump.
10. Connect electric power supply to the equipment, and connect bowl motor, conveyor motor,
and feed pump motor to terminal blocks inside control cabinet.
11. Connect sensor cable to sensor junction box.
12. For explosion-proof cabinet, connect compressed air supply source to purge unit.
13. Refer to Section 4 for startup and operating procedures.
REQUIRED CLEARANCES AND POSITIONING
Sufficient space should be provided around the equipment to facilitate access for maintenance,
inspection, and adjustment.
Typical operation and maintenance functions include the following activities:
1. Access and operate the system control panel.
2. Open and close the control cabinet door (Figure 3-1).
3. Open and close top cover.
4. Grease rotating assembly bearings.
5. Check and fill gearbox.
6. Connect and disconnect feed and liquid discharge lines.
7. Remove and install feed tube.